Retainage is a percentage of each progress payment, commonly 5% to 10%, that a customer holds back until work is finished or a milestone is reached. It protects the owner but ties up the contractor's cash. Track it separately as retainage receivable (held from you) and retainage payable (held from subs).
What is retainage in construction?
Retainage (also called retention) is a share of each progress payment that the customer holds back until the work, or a stage of it, is finished. It is meant to give the owner some protection if the work is incomplete or has defects. The contract sets the rate and the release terms.
It applies up and down the chain. A customer may hold retainage from you, and you may hold retainage from your subs.
How much is typical, and when is it released?
A common range is 5% to 10% of each payment, per a retainage guide from Levelset. The same source notes that retainage is often held through the whole project and released after substantial completion, though the contract can set milestone releases. Rules vary by state, by project type and between private and public work. Some states limit how much can be held, and some set specific requirements. Check your contract and confirm the rules with an attorney or your CPA. We do not give legal advice.
How does retainage work on a real job?
Illustrative example. A $200,000 remodel with 10% retainage. You bill $40,000 for a progress draw. The customer holds $4,000 (40,000 x 10%) and pays $36,000. By the end of the job, $20,000 (200,000 x 10%) has been held. If the job's net profit is 8% of contract, or $16,000, the retainage held is bigger than your profit on the job. That is the part many owners miss.
Now look at the sub side. If your framing sub has a $50,000 contract and you hold 10%, you hold $5,000 until you release it. If you pay subs in full while your customer holds back, you finance the gap yourself.
How should you account for retainage?
The principle is simple: keep it visible. Do not let retainage disappear inside accounts receivable.
- Retainage receivable. Amounts a customer has held from your billings. Track by job. Report it separately from regular receivables so you know what is collectible now.
- Retainage payable. Amounts you have held from subs. This is a liability until released.
- Invoices show gross, held and net. Each draw shows the work billed, the retainage held and the net due.
- Revenue and timing. How retainage affects reported revenue depends on your accounting method. Ask your CPA how it should be treated for your financials and taxes.
It also feeds your WIP report. Billings to date should be gross of retainage, so percent-complete comparisons stay accurate. See the WIP report guide.
Why does retainage matter more on small jobs than you would think?
Larger firms have credit lines and finance staff to absorb the delay. An owner-led remodeler often has neither. Ten percent of a $200,000 job is $20,000, which can be a month of payroll. The money is not lost, but it is not available either, and if two or three jobs reach closeout in the same quarter, the effect on cash adds up.
How does retainage hurt cash flow, and what can you do?
You pay labor, subs and suppliers as you go. The customer holds the last 5 to 10% until the end. On a long job, that is a lot of your own money outstanding. Steps that can help:
- Know the number. List retainage receivable by job and the expected release date. Include it in your cash flow forecast.
- Negotiate terms in the contract. Options include a lower rate, a reduction at a set percent complete, or release when a defined stage is accepted. Some contracts allow this. Ask before signing.
- Flow terms down fairly. If you hold retainage from subs, state it in the subcontract and release on the same trigger you are paid on.
- Define completion. Write down what substantial completion means and how punch-list items affect release.
- Bill for release promptly. Invoice the release as soon as the trigger occurs and follow up. Retainage often goes unpaid just because nobody asked.
- Ask about alternatives. Some owners accept a bond or other security instead. Whether that fits depends on your cost and the owner.
Where you have a payment dispute, talk to a construction attorney. Lien deadlines and notice rules are strict and differ by state.
What mistakes do contractors make with retainage?
- Treating it as profit that arrives later. It is money you have earned but not collected, and it often arrives after you have already paid the costs behind it.
- Ignoring it in the cash forecast. A job can look fully billed while 10% of it is a long way from your bank account.
- Holding it from subs without saying so. If the subcontract does not state it, you may have a dispute and a damaged relationship.
- Losing track of release conditions. Closeout paperwork, warranties and final lien waivers often trigger release. If nobody owns the list, release slips by months.
- Mixing retainage with change orders. Approved changes raise the contract value, so the retainage held on them should be tracked too.
A checklist for each job
- Retainage rate and release trigger written in the contract.
- Same terms stated in each subcontract.
- Draw invoices showing gross, retainage and net.
- Retainage receivable and payable tracked by job.
- Release date on your cash forecast.
- Release invoice sent and followed up.
How does DeeperBench help?
Retainage tracking is part of our construction bookkeeping: separate receivable and payable ledgers by job, draw invoices that match your contract, and release dates in the cash forecast. A person reviews each month's close. We do not give legal advice or handle lien notices. For how this fits in our finance work, see the finance service overview or ask us a question.
Common questions
Is retainage the same as a deposit?
No. A deposit is paid up front before work. Retainage is withheld from payments for work already done and released later.
Is retainage legal on residential remodeling?
It depends on your state and contract. Some states limit it and some restrict it on certain project types. Check with a construction attorney before relying on it.
When should I invoice for retainage?
As soon as the contract's release trigger occurs, such as substantial completion or acceptance of a stage. Do not wait for the customer to bring it up.
How does retainage affect my taxes?
It can affect when income is reported, depending on your accounting method. That is a question for your CPA.