WIP report for contractors: how to build and read one

A WIP report for contractors lists every open job with its contract value, estimated cost, cost to date, percent complete, revenue earned and amount billed. The difference between earned and billed shows whether a job is overbilled or underbilled. Use it monthly to spot margin problems and cash timing early.

What is a WIP report?

A work in progress (WIP) report, also called a WIP schedule, is a list of every open job with its contract value, estimated total cost, cost to date, percent complete, revenue earned, amount billed, and the gap between the last two. It answers three questions: how much of each job have we really done, how much have we billed, and what margin is the job heading toward.

It is not an invoice list or a P&L. A P&L tells you what happened this month. A WIP report tells you where each open job stands against its contract, which is what banks, sureties and good owners look at.

How do you calculate percent complete?

The common method for small contractors is cost-to-cost. Percent complete equals cost to date divided by estimated total cost. Multiply that by the contract value to get revenue earned to date. Then compare with what you have billed.

  1. Start with the current contract value, including approved change orders.
  2. Estimate total cost at completion. Update it when scope or prices change.
  3. Divide cost to date by that estimate.
  4. Multiply the result by contract value for earned revenue.
  5. Subtract earned revenue from billings to date. Positive means overbilled, negative means underbilled.

Some firms use other measures, such as units installed or a project manager's physical estimate. Which method you use for financial statements is a question for your CPA, since it affects how revenue is reported.

What does a WIP report look like?

Illustrative example. Three open jobs. Arithmetic: percent complete = cost to date / estimated cost; earned = percent x contract.

JobContractEst. costCost to date% completeEarnedBilledOver / (under)
Kitchen$100,000$70,000$35,00050%$50,000$60,000$10,000 over
Bath + deck$80,000$60,000$45,00075%$60,000$48,000$12,000 under
Addition$150,000$110,000$22,00020%$30,000$45,000$15,000 over

Total overbilled is $25,000 and total underbilled is $12,000, so the company is net $13,000 ahead of its work. That cash is real, but it is owed back in the form of work still to do. If the addition's cost estimate is too low, the overbilling hides a coming margin problem.

What do overbillings and underbillings tell you?

Overbilled means you have collected, or can collect, more than you have earned. It helps cash now. It can also hide a job whose costs are rising faster than the estimate, or costs that have not been entered yet, such as sub invoices still on their way. Growing overbillings across many jobs mean you may be financing today's payroll with next month's work.

Underbilled means you have earned more than you have invoiced. It is effectively a loan to the customer. Usual causes are late billing, approved changes not yet invoiced, and cost overruns. A CPA-authored piece from Providence Business News calls out cost overruns as the most worrying cause.

Watch the trend, not just the total. A job that is underbilled for three months in a row needs a conversation.

What makes a WIP report misleading?

The usual culprit is the estimate to complete. Take the kitchen job above. If its real total cost is $85,000 instead of $70,000, the picture changes:

  • Percent complete drops from 50% to about 41% (35,000 / 85,000).
  • Earned revenue falls from $50,000 to about $41,176.
  • Overbilling grows from $10,000 to about $18,824 (60,000 less 41,176).
  • Projected margin falls from $30,000, or 30%, to $15,000, or 15% (100,000 less 85,000).

Nothing about the bills changed. Only the estimate did. That is why the project manager's honest estimate to complete matters more than any formula. Other common errors are missing sub invoices at month-end, change orders approved verbally but not written down, and costs coded to the wrong job.

How often should you update it?

Monthly is the minimum, after the books are closed. Active jobs with fast-moving costs benefit from an interim look every week or two. The report is only as good as two inputs: current cost data and a current estimate to complete. A stale estimate makes percent complete look better than it is.

Checklist before you trust the report

  • All vendor and sub bills through month-end are entered against the right job.
  • Approved change orders are in the contract value and in the estimated cost.
  • Estimate to complete was reviewed by the project manager this month.
  • Billings to date match the invoices actually sent, including retainage.
  • Jobs marked complete have final costs posted.

Who else reads your WIP report?

Lenders and sureties often ask for one when you apply for a line of credit or bonding. They tend to look at the pattern across jobs, not just the total, and at whether estimated margins hold from month to month. If a job's projected margin drops every month, expect questions. A report you already produce every month, with a documented method, is easier to defend than one rushed together for an application. If a lender needs a formal statement, your CPA prepares it. We would not sign one.

Where does this fit with the rest of your finances?

A WIP report sits on top of job costing and clean bookkeeping. Without job-coded costs, you cannot compute it. See our guides to retainage and setting up a chart of accounts for the foundation. Our finance service produces a WIP report as part of the monthly close with job costing. A person reviews it before you see it. If you would like to see one built from your own jobs, get in touch.

Common questions

What is the difference between a WIP report and a job cost report?

A job cost report compares costs with budget. A WIP report adds contract value, percent complete and billings, so you can see whether each job is over or under billed.

Is overbilling bad?

Not by itself. It improves cash. It becomes a problem when it hides rising costs or grows across many jobs, because that cash is owed back in work still to do.

Which percent complete method should I use?

Cost-to-cost is common and simple. The right method for your financial statements is a question for your CPA, since it affects how revenue is reported.

Do small remodelers need a WIP report?

If you have several overlapping jobs, yes. With one or two jobs, a budget-vs-actual sheet may be enough.